Projects
Hydropower Plant
North Macedonia
• Replacement, wiring, testing and commissioning of numerical protection relays
• Installation of GE protection relays (GE L90, GE L60)
• Implementation of remote control and SCADA signalling
Measurement cabinet for substation Pristina, Kosovo
• Supply, assembly and installation of energy meters (Landis+Gyr, ZMQ)
• Testing and delivery of electrical energy measurement cabinet (110 kV)
Hydropower Plant Globočica
North Macedonia
• Replacement of motor drives on 110 kV disconnectors
• Replacement, wiring, testing and commissioning of numerical protection relays
• Installation of GE protection relays (GE L90, GE L60)
Substation Ferizaj
(Uroševac) – Kosovo
• Replacement of motor drives on 110 kV disconnectors
• Cable connection, testing, functional testing and commissioning
• Signal integration into BCU unit for SCADA system
Kaufland Zadar – Croatia
• Electrical installation works for Kaufland facility
• Reconstruction, testing and commissioning of the facility
• Dismantling of existing electrical equipment and installation of new systems
Donji Miholjac Substation
110 kV – Croatia
• Installation of RTU for remote meter reading
• Implementation of measurement data into SCADA central system
• Reading of pulse measurements from Landis+Gyr / ZMQ meters
Globočica Substation
North Macedonia
• Installation of protection cabinet for 110 kV system (HPP Globočica)
• Cable laying, connection and testing
• Implementation of protection and control signals into SCADA system
Kavadarci Hydropower Plant
North Macedonia
• Replacement, wiring, testing and commissioning of numerical protection relays
• Installation of GE protection relays (GE L90, GE L60)
• Testing of SMT and NMT systems for numerical protection
Mostar 2 Substation 110/35 kV
Bosnia and Herzegovina
• Testing of control, measurement and protection cable connections
• Functional testing of feeder bays, transformer bays, measurement and protection systems
• Installation, testing and commissioning of ABB protection relays (REL647, REC670....)
Gjakova (Đakovica) Substation 110/35 kV – Kosovo
• Replacement of motor drives on 110 kV disconnectors
• Replacement of 110 kV circuit breaker (SIEMENS 3APFG-123kV)
• Cable connection, testing, functional testing and commissioning
Poreč Substation
110 kV – Croatia
• Procurement and assembly of control and protection panels for capacitor bank bay
• Transport, delivery and installation of equipment and panels
• Testing and commissioning of installed equipment
UNIOR Vinkovci Solar Power Plant – 500 kW Grid Connection
• Connection of solar power plant to 0.4 kV grid via transformer
• Inverter parameterization and implementation of remote (cloud) monitoring
• Testing and commissioning in cooperation with HEP-ODS